Body carcass and front flap: shell – U11 (integration and new systems)
Date: 2019 to 2021
Contracting entity: BMW – plant engineering
End customer/site of installation: BMW Regensburg
Plants such as:
KG1, KG1-AS, WL, HFR (integration) I KG2, KG2-AS (integration) I KG3, KG3-AS (integration) I Roof system (integration) | Front flap (new system) I Measuring cells GOM (new system)
Project description:
- Entire electric planning (hardware construction, software project planning)
- Control cabinet construction
- Provision of control technology
- Assembly and installation
- Robot programming
- Commissioning
Technologies (excerpt):
30 pieces S7-400 with CPU 416 | 30 pieces visualization with Zenon on PC 627 | 50 pieces control units with Zenon visualization | 250 pieces ABB IRC5 industrial robots (integration)