Body Carcass and Side Frame V8: Shell – G72 (Integration)

Date: 2023 to 2024
Contracting entity: TMS Turnkey Manufacturing Solutions GmbH
End customer/site of installation:  BMW Dingolfing

Plants such as:

  • Body carcass 1 (integration)
  • Body carcass 2 (integration)
  • Body carcass 3 (integration)
  • Body carcass 3 – welding (integration)
  • Side frame – inside (integration)
  • Side frame – middle (integration)
  • Side frame – outside (integration)

Project description: 

  • Entire electric planning (hardware construction, software project planning)
  • Control cabinet construction 
  • Provision of control technology
  • Assembly and installation 
  • Robot programming 
  • Virtual commissioning, physical system start-up

Technologies (excerpt):

  • 18 pieces S7-1500 with CPU 1518F – PN/DP
  • 18 pieces Visualization with WinCC on PC 677
  • 35 pieces Visualization with WinCC on PC 477E
  • 70 pieces Control units with WinCC visualization
  • 76 pieces KUKA KRC4 industrial robots … in the body carcass range
  • 60 pieces KUKA KRC4 industrial robots … in the side frame range